The construction work of the Cathedral of Our Lady of Arabia is continuing by the grace of God, and thanks to the hard work of the building team and with your commitment to this project. Much of the exterior and interior work centered around the cladding, water-proofing and painting works. Please continue to support the work of the Cathedral by your monetary and prayerful support. Thank you and God bless you.

FRONT ELEVATION ENTRANCE WORKS

ENTRANCE FLOORING WORKS

AUDITORIUM LIGHT WEIGH SCREED WORKS

DOME CURTAIN WALL MOCK-UP

ROOF WATERPROOFING PU FOAM WORKS

ROOF WATERPROOFING LIGHT WEIGHT SCREED WORKS

SPIRE ROOF TILE WORKS

AUDITORIUM WATERPROOFING ROOF PU FOAM WORKS

EXTERNAL STONE CLADDING WORKS

BOUNDARY RETAINING WALL STONE CLADDING WORKS

STEEL DOOR INSTALLATION WORKS

INSTALLATION OF WOODEN DOORS

EXTERNAL PAINTING WORKS

EXTERNAL BOUNDARY WALL PAINTING WORKS

BALCONY LEVEL GYPSUM CEILING CLOSING WORKS

CATHERDRAL IGLU WORKS AT GROUND FLOOR

PAINT PREPARTION FOR CONFESSIONAL CHAPEL AREA

PAINT PREPARATION FOR MAIN SACRISTY AREA